Niche substance · lead times

The register we keep, so nothing waits on a delivery

Weeks are from order release to delivery for the Seattle market, and they are sample figures that move. The order-by column is the part that matters: it names the milestone by which an item has to be on order.

A close-up of interior design planning with material samples on a marble table.
Cabinetry, windows and the utility are the three that decide finish dates.

Lead times by category

Twenty-two lines, grouped the way we buy them. The risk column is how likely that item is to become the critical path on a whole-home job.

CategoryItemWeeksOrder byRisk
CabinetryStock cabinetryAvailable in fixed sizes. Filler strips do the fitting.3 to 5At permit issueLow
CabinetrySemi-custom cabinetrySizes to the inch, limited door and finish range.8 to 12At permit issueMedium
CabinetryFull custom millworkThe single most common cause of a delayed finish date. Shop drawings must be approved against framed dimensions.14 to 22Before permit submissionHigh
Windows and doorsStock vinyl windowsFine for secondary elevations and basements.4 to 6Before framing startsLow
Windows and doorsClad wood windowsFraming cannot be closed until these are in and installed.10 to 16At permit issueHigh
Windows and doorsExterior doors, customRough opening depends on the actual unit, so the order drives the framing.12 to 20Before permit submissionHigh
Windows and doorsInterior doors, stock2 to 4Before drywallLow
AppliancesMainstream appliance packageSpecs are needed early even if delivery is late, because cabinetry is built to them.2 to 6Before cabinet fabricationLow
AppliancesPanel-ready and professional appliancesPanel dimensions and hinge requirements change the cabinet order.10 to 26Before cabinet fabricationHigh
StoneSlab selection at the yardSlabs are tagged and held. Hold fees apply after 30 days at most yards.1 to 2During rough-inLow
StoneFabrication after templatingNever templated from drawings. The clock starts when the cabinets are level.2 to 3Template after cabinets are setMedium
TileStocked domestic tile1 to 2Before waterproofingLow
TileImported or made-to-order tileDye lots matter. Order the whole quantity plus waste in one go.8 to 14At permit issueHigh
FlooringStocked engineered hardwoodAdd acclimation time in the conditioned house on top of the lead time.2 to 4Four weeks before install, for acclimationLow
FlooringCustom milled or wide-plank flooring8 to 12During rough-inMedium
PlumbingStandard fittings and fixturesValve bodies are needed at rough-in even though trim goes on at the end.2 to 4Before rough-inLow
PlumbingSpecialty finishes, unlacquered brassBack-ordered finishes are common. Confirm the valve body ships separately.8 to 16Before rough-inHigh
MechanicalHeat pump and air handlerEquipment must be on site for the rough inspection in most jurisdictions.4 to 10Before rough mechanicalMedium
ElectricalPanel, meter base and utility coordinationThe utility's schedule, not ours. A service upgrade can hold a whole project.6 to 16At permit issueHigh
StructuralLVL and PSL beams1 to 3Two weeks before the shoring goes upLow
StructuralFabricated structural steelShop drawings and a fabrication slot. Confirm access into the room before ordering.4 to 8At permit issueMedium
LightingDecorative and imported lightingJunction box locations and mounting hardware depend on the fixture.10 to 16Before drywallMedium

CabinetryWindows and doorsAppliancesStoneTileFlooringPlumbingMechanicalElectricalStructuralLighting

When the budget will not carry everything

Phasing a multi-room renovation across a budget

Phasing works when the order is right. Everything behind the walls comes first, because it cannot be added later without opening finished surfaces. Rough-in for later phases is stubbed during phase one.

  1. Phase one · 45 to 55 percent of the total

    Everything behind the walls

    Structure, roof, windows, electrical service, mechanical and plumbing distribution. None of it shows, all of it is impossible to add later without opening finished walls.

    • Beams and footings
    • Roof and envelope repairs
    • Panel and service
    • Heat pump and ducting
    • Rough plumbing and drainage
    • Insulation and air sealing
  2. Phase two · 30 to 35 percent

    The rooms you live in daily

    Main-floor finishes, the primary bathroom, flooring across the level and the room where the household actually gathers.

    • Main-floor flooring
    • Kitchen and main living finishes
    • Primary bathroom
    • Interior doors and trim
    • Paint on the main level
  3. Phase three · 15 to 25 percent

    The rooms that can wait

    Basement fit-out, secondary bathrooms, the deck and landscaping. All of it can be built later without disturbing phase one or two, as long as the rough-in was stubbed for it.

    • Basement finishing
    • Secondary bathrooms
    • Deck and outdoor living
    • Built-ins and joinery
    • Landscape and drainage

Percentages are sample allocations for a whole-home renovation and will differ on your house. The sequence will not.

Answers

Lead-time questions

Not answered here?Ask us directly

Long-lead items go on order the week the permit is issued, not the week demolition starts. Cabinetry, clad wood windows and anything involving the utility are the three that most often decide the finish date.

We hold a submittal and lead-time register per project. If a date moves, you hear it from us within a day, with the knock-on effect on the schedule named rather than absorbed quietly.

For decorative lighting and some plumbing fittings, yes. We cannot warrant owner-supplied items, and a late delivery of one is an owner-caused delay under the contract.

Because it is not templated until the cabinets are set, shimmed and level, and fabrication then needs a slot in the shop. Two to three weeks after template is normal and is scheduled, not hoped for.

Sometimes, in storage or a deposit. It costs far less than a crew standing down for three weeks waiting for windows.

Material samples laid out in the design studio

Next step

Start with a walk-through, not a price

Ninety minutes in your house. We look at the crawlspace, the attic and the panel before we look at the kitchen, and you leave with a budget band you can plan around.