Interior painting

Finish carpentry, prep and coats, as the last structural act.

Typical band
$4.50 to $9.00 per square foot of wall (sample band)
Duration
2 to 4 weeks on a whole level
A woman stands on a ladder painting a wall white, part of a DIY home renovation.

What this work really involves

Painting is the trade everyone thinks they understand and the one that most visibly reveals what happened underneath. A wall that was not skim coated, a corner bead that was not set, a nail pop that was not fixed, all of it shows up in the second coat under raking light.

Our painters come after the drywall is finished to a defined level, the trim is installed and caulked, and the site has been vacuumed. On any house built before 1978 we work under lead-safe renovation practices, including containment and HEPA cleanup.

Permit path

No permit; lead-safe practices required by federal rule on houses built before 1978

What is included

  • 01

    Surface preparation

    Nail pops set and patched, seams checked under raking light, corner beads verified, sanding between coats.

  • 02

    Trim and caulk

    Every inside corner and trim-to-wall joint caulked, nail holes filled and sanded before priming.

  • 03

    Priming

    Full prime on new drywall and on any patched surface, with a stain-blocking primer where tannin or smoke is present.

  • 04

    Sheen schedule

    A documented sheen per surface: ceilings, walls, trim, doors, and wet rooms, so touch-ups match years later.

  • 05

    Lead-safe practice

    On pre-1978 houses, containment, wet methods, HEPA vacuums and a cleaning verification at the end of each work area.

  • 06

    Leave-behind record

    Colour, product, sheen and room list handed over at closeout, with labelled touch-up cans.

How the stages run

  1. 01

    Colour review

    Large samples painted on site and looked at in morning and evening light, not chosen from a chip.

  2. 02

    Prep

    Three to six days. Protection, patching, sanding, caulking.

  3. 03

    Prime

    One to two days.

  4. 04

    Trim and doors

    Three to six days, usually sprayed and back-rolled or brushed depending on the profile.

  5. 05

    Walls and ceilings

    Four to eight days for two coats on a whole level.

  6. 06

    Touch-up

    Ongoing through the punch list and after floor protection comes up.

What moves the price

Wall condition
A skim coat on a textured wall you want flat is a separate and significant line item.
Trim quantity
Doors, casing, base, crown and built-ins are priced by count and profile, not by floor area.
Ceiling height
Anything over nine feet adds staging time.
Colour change
A deep colour over white, or white over a deep colour, often needs a third coat.
Occupied work
Containment, daily cleanup and shorter working windows add labour.

Two things we will always tell you

Paint late. A room painted before floors, fixtures and glass go in will be touched up twice, and the second touch-up rarely matches perfectly on a flat sheen.

Keep a labelled touch-up can per room. We hand them over in the closeout binder.

Answers

Interior painting: common questions

Not answered here?Ask us directly

Because flattening an existing textured wall is a plastering operation, not a painting one. We price it honestly rather than bury it.

We usually specify a washable matte on walls and a satin or semi-gloss on trim and doors. The full schedule is in the closeout binder.

Yes, with low-VOC products and ventilation. On pre-1978 houses we use lead-safe containment regardless of whether you plan to test.

We can scan a chip, but scanned matches drift. If the original product and code are known, that is always better.

Material samples laid out in the design studio

Next step

Start with a walk-through, not a price

Ninety minutes in your house. We look at the crawlspace, the attic and the panel before we look at the kitchen, and you leave with a budget band you can plan around.