Education Hill, Redmond · 2025

Raising a ceiling under an engineered truss roof

A 1994 truss roof modified to a scissor profile over the living space, with a manufacturer's modification letter and a full shear recalculation.

Scope
Main-floor rework with truss modification
Budget band
$245,000 to $280,000 (sample band)
Duration
11 months, design through closeout
Occupied
Occupied, apart from six weeks.
Interior of modern white flat furnished with comfortable couch and dining zone with wooden floor and white walls

How it went

You cannot cut an engineered truss. The web members are doing calculated work, and removing one changes the behaviour of the whole assembly. The only legitimate routes are a modification design from the original manufacturer or replacement trusses.

We tracked down the original truss supplier from a stamp on a web member in the attic, and they produced a modification design for a scissor profile over the living room. That took five weeks and it was the critical path for the entire project.

Once the design existed, the work itself was straightforward: temporary support, modification in sequence, inspection, then insulation and drywall to the new profile.

The ceiling went from 8 feet flat to 11 feet 4 inches at the peak. The room is unrecognisable and not one structural member was guessed at.

By the numbers

  • 3 ft 4 inCeiling height gained
  • 5Weeks to get the truss letter
  • 7Trusses modified
  • 6Weeks the family moved out

Three contractors said they would just cut the trusses. Atelier explained why that is illegal and then found the original manufacturer.

Hana YoshidaEducation Hill, main-floor rework
Material samples laid out in the design studio

Next step

Start with a walk-through, not a price

Ninety minutes in your house. We look at the crawlspace, the attic and the panel before we look at the kitchen, and you leave with a budget band you can plan around.

Cookie preferences

Choose which cookies you allow. You can change this at any time from the link in the footer.